Outage Season Part 1

Outage Season Part 1

Accurity is supporting 3 back to back outages for our customers on HRSG's. Outage #1 - Provide replacement of 25 #thermowells, from Stainless to P-91, remove creep in the heat affected zone of 3 - 16" x 10" WOL's, and provide other miscellaneous valve replacement...

PipingValves
Accurity Industrial Contractors
Valve Installation

Valve Installation

Do you have valves that need to be installed?  This is a 12" cooling water line for one of our customers in southern Indiana. The new valve was a little bigger than the old valve. Accurity had to cut the water line and move it to accommodate the new valve. Let...